Construction of the Hilliard Triangle will begin in May
2010. Work will continue through the fall of 2011. Work by private utility
companies (AEP, AT&T, Columbia Gas, Time Warner, WOW, etc.) commenced in the
fall of 2009 and will continue throughout the summer of 2010. These utility contractors
do not work directly for the City of Hilliard; however, the City is working to coordinate
the work between multiple private and public contractors.
The City of Hilliard work is divided into four phases as depicted in the diagram
below:
|
|
|
|
|
Phase 1 (Summer 2010)
|
During the summer of 2010, the City’s project and work by AEP to relocate poles
and overhead lines will take place concurrently. AEP will be working along the west
side of Main Street near the Hilliard United Methodist Church and along Scioto Darby
Road near Donatos and in front of Memorial Middle School during this time.
The City’s
crews will be working at the Main Street/Cemetery Road intersection. The City and
AEP are working together to minimize the disruption to the public. Scioto Darby
Road will be open for east/west traffic during this time; Cemetery Road will be
closed.
Roadway work surrounding Hilliard Station Sixth Grade School is expected
to take place during this phase. The goal is for this work to be complete by the
time school starts in late August 2010.
|
|
Phase 2 (Fall 2010)
|
During the fall of 2010, the section of Scioto Darby Road near
The Laurels (formerly The Arbors) will close
to construct the signalized intersection of Scioto Darby/Cemetery.
|
|
Phase 3 (Fall 2010 – Spring 2011
) |
Beginning in the fall of 2010, the City’s crews will be working at the intersection of Main Street/Scioto Darby Road.
|
|
Phase 4 (Summer 2011)
|
Roadway work along Scioto Darby Road surrounding Memorial Middle School is expected to take place during the summer of 2011.
|
Click here for the latest Road Closings & Detours
|